This time schedule will be adjusted frequenly to reflect increasing detail of the organisation of possible future campaigns. Come back soon!


Schedule (2002 Leonid MAC):
  • January 1, 2002 and prior - Re-define Leonid MAC approach in contacts with aircraft management, participating researchers, and program managers
  • April 7-14 - Astrobiology Science Conference, NASA Ames, CA
  • May 2-5 - 2002 Leonid MAC Workshop, Tokyo, Japan
  • June 28 - Papers submitted on results prior campaign for special issue "Astrobiology"
  • July 1 - Requests for year 02 funds from NASA/ASTID program and NASA Planetary Astronomy program
  • July 1 - NASA/Ames-SETI Cooperative Agreement in place
  • July 08-July 12 - Bioastronomy meeting, Hamilton Island, Australia
  • July 29-Aug 02 - 2002 Asteroids, Comets, Meteors meeting, Berlin, Germany
  • July 29 - Request foreign Op Rights (FISTA)
  • Aug 02 - Local funding ASUR deployment and postdoc position in place
  • August 11 to 13 - Field tests for instruments and outreach activities during Perseids
  • August 18 - Notify organizations of Passport/VISA requirements
  • August 20 - foreign national clearances in place
  • August 20 - ESA funding in place, ASUR support secure
  • Aug 31 - Contributions for workshop proceedings due.
  • Sept 03 - Funding in place for DC-8 deployment
  • Sept 03 - Start formal program, finalize route
  • Sept 03 - Start prepare deployment of new submm receiver for 2002 Leonid MAC
  • Sept 05 - Mission patch design posted
  • Sept 11 - Funding in place for FISTA deployment
  • Sept 20 - Floorplan DC-8 review (visit NASA Dryden)
  • Sept 23 - Website update 508 compliance completed
  • Sept 23 - Finalize itinerary
  • Sept 23 - mission patches ordered
  • Sept 27 - Mission planning completed, instruments/personnel decided
  • Sept 27 - Coordinate any Foreign Official Observers
  • Sept 27 - Experiment plan in place, floorplan in place for DC-8.
  • Oct 04 - clearances foreign nationals submitted/contact embassies
  • Oct 04 - flight suits ordered
  • Oct 04 - SETI-NASA Dryden work agreement in place
  • Oct 04 - Outreach team in place
  • Oct 05 - Coordination meeting and practise session flux measurement team
  • Oct 12 - Lodging arrangements installation period Edwards AFB in place
  • Oct 12 - Invitation letters out - Send passports out for VISA's (as required)
  • Oct 12 - Nametags ordered
  • Oct 12 - Instrument parts ordered, gear assembled.
  • Oct 12 - Review papers completed
  • Oct 16 - MOU's drafts to participating researchers
  • Oct 16 - Special Leonids session at the COSPAR/World Space Congress, in Houston, TX. Video material collected.
  • Oct 16 - Camera provided for ground-based submm experiment
  • Oct 21 - Leonid MAC Flux Estimator updated
  • Oct 22 - Coordinate lodging/transportation (as required)
  • Oct 22 - Coordination SETI outreach
  • Oct 22 - Request overflight clearances
  • Oct 22 - Commercial flights to Edwards AFB booked
  • Oct 22 - Coordinate aircraft ground support requirements
  • Oct 22 - Coordinate airspace requirements
  • Oct 22 to 23 - Instrument Field tests during Orionids/Taurids
  • Oct 24 - Coordination ground-based support Spain/Mnt Lemmon
  • Oct 24 - Coordination video uplink
  • Oct 25 - Shipment flux measurement unit
  • Oct 28 - Shipment camera to Spain
  • Oct 28 - Precoordination meeting
  • Oct 28 - Export control paperwork in place
  • Oct 31 - CCB SR Review (DC-8)
  • Nov 1 11:00 am PST - NASA Astrobiology Institute Seminar Lecture on Leonid shower
  • Nov 1 - check flight currencies for non test wing personnel
  • Nov 1 - Send intended support plan
  • Nov 1 - Receive crewlists
  • Nov 1 - USAF SOC in place

    Instrument installation phase:

  • Oct-Nov - Stewart Rad. Lab. deployment to Edwards
  • Nov 4 - NASA 7 Delivery of instruments
  • Nov 4-8 - P.I. at NASA Dryden/Edwards AFB
  • Nov 5 - visit clearances issued
  • Nov 5 - remaining funding issues solved
  • Nov 5 - SOC approved
  • Nov 4 - Lodging/transportation in place
  • Nov 6 - DC8 Tech Brief
  • Nov (6-8, +) 12-14 - Payload integration FISTA
  • Nov 7-8, + 12 - Payload Integration DC-8
  • Nov 7 - Prepare TDY orders
  • Nov 8 - Squadron commander briefing
  • Nov 8 - international clearances issued
  • Nov 9, DC8 payload integration contingency day
  • Nov 11 - SETI-Researcher work agreements in place
  • Nov 12 - Technical flight crew briefing FISTA
  • Nov 12 - Powerup DC8
  • Nov 13 (We.) - Roll out, photo lab (DC-8)
  • Nov 14 (Th.) - afternoon Shakedown flight DC8

    Mission phase:

  • Nov 14 - Badging no later than 15:00 at NASA Dryden
  • Nov 14 - 17:30-19:30 Experiment Test Flight (2.0 hr) DC-8.
  • Nov 14/15 - good night sleep (8h minimum)
  • Nov 15 (Fr. noon) - *Mandatory Safety Brief*.
  • Nov 15 17:30 Departure Edwards AFB to Offutt AFB (FISTA + DC8)
  • Nov 16 (Sa) 19:00 departure Offutt AFB to Torrejon AFB Spain (arr. 10:30), shakedown flight
  • Nov 17 to 19 - web event (http://leonid.arc.nasa.gov)
  • Nov 18 (Mo)
  • Nov 19 (Tu) 03:30 departure Torrejon AFB to Offutt AFB, Nebraska (arr. 06:18), main mission flight
  • Nov 19 good night rest, early start of day Nov 20
  • Nov 20 (We) 05:00 departure Offutt AFB back to Edwards AFB (arr. 05:48)
  • Nov 20 download and demod FISTA
  • Nov 20-21 dowload and demod DC8

  • July-Aug, 2003 - Leonid MAC Workshop and Meteor Storm science meeting
[Mission now complete]



 